Case Studies
Indoor Air Quality / Real Estate Operations
Case Study: New Orleans Job Corps Center
New Orleans, LA
The Issue: Pervasive Mold Contamination
The Solution: Facility Decontamination with ClO2 Gas
On March 18, 2006, Sabre fumigated the New Orleans Job Corps Center located in New Orleans, LA. The building was fumigated with chlorine dioxide (ClO2) gas for the purpose of treating the pervasive mold contamination present within the building. The 45,000 square foot fumigation was completed in two days including building encapsulation. The two other buildings at the center were also fumigated earlier in the week.